Amey Highways ASC 6 and 8 Contract

Bos Projects Consultancy Ltd on secondment from Systech Internal provided commercial management services on this project. We were involved in compensation events, delay analysis, subcontractor account management & settlement, preparing and agreeing project final accounts with Highways England.


 
 

A12 Olivers Bridge Refurbishment

Refurbishment work to Olivers Bridge, which carries the A12 over the B1018 Maldon Road just to the east of Witham was undertaken to include waterproofing the bridge deck, replacing the bridge joints, improving the drainage and resurfacing.

Bos Projects Consultancy provided Commercial support to Amey Highways.

Our Value
  • Contributed to Amey’s assessment of subcontractor’s valuations and payment applications
  • Final Accounted subcontractors accounts and back-charges applied where necessary.
  • Liaised with project team and priced compensation Events
  • Prepared and submitted all back-up information's to support Compensation Events
  • Prepared delay analysis programme to back up Compensation Events
  • Final Accounted and closed out project

A14 Ipswich, Suffolk: Orwell Bridge safety improvements

Scheme was the introduction of new speed limit, improving road markings and installing new traffic signs as part of a package of measures to improve safety on the A14 Orwell Bridge. This work also included the installation of average speed cameras enforcing a new speed limit of 60mph. Bos Projects Consultancy provided Commercial support to Amey Highways.

Our Value
  • Contributed to Amey’s assessment of subcontractor’s valuations and payment applications
  • Final Accounted subcontractors accounts and back-charges applied where necessary.
  • Liaised with project team and priced compensation Events
  • Prepared and submitted all back-up information's to support Compensation Events
  • Prepared delay analysis programme to back up Compensation Events
  • Final Accounted and closed out project

M11 and A120 Stansted Airport road repairs

This Project included resurfacing parts of the M11 and A120, as part of a package of works. The package of works included putting in new signs to make the road easier to navigate, repairing an embankment on the M11 at junction 6 (M25) by removing and replacing with new material to make the embankment more secure and reduce the risk of flooding.

Bos Projects Consultancy provided Commercial support to Amey Highways.

Our Value
  • Contributed to Amey’s assessment of subcontractor’s valuations and payment applications
  • Final Accounted subcontractors accounts and back-charges applied where necessary.
  • Liaised with project team and priced compensation Events
  • Prepared and submitted all back-up information's to support Compensation Events
  • Prepared delay analysis programme to back up Compensation Events
  • Final Accounted and closed out project

A5 Dunstable North

The work included the installation of a new toucan crossing, installing new kerbs, edgings and paving, signage, and lining to its approaches on A5 between junctions of Winfield Street and Regents Street.

Bos Projects Consultancy provided Commercial support to Amey Highways.

Our Value
  • Contributed to Amey’s assessment of subcontractor’s valuations and payment applications
  • Final Accounted subcontractors accounts and back-charges applied where necessary.
  • Liaised with project team and priced compensation Events
  • Prepared and submitted all back-up information's to support Compensation Events
  • Prepared delay analysis programme to back up Compensation Events
  • Final Accounted and closed out project

A1(M) Huntingdon to Peterborough: overhead signs replacement

The Scheme was replacing the overhead message signs on the A1(M) between Huntingdon and Peterborough with new models.

Bos Projects Consultancy provided Commercial support to Amey Highways.

Our Value
  • Contributed to Amey’s assessment of subcontractor’s valuations and payment applications
  • Final Accounted subcontractors accounts and back-charges applied where necessary.
  • Liaised with project team and priced compensation Events
  • Prepared and submitted all back-up information's to support Compensation Events
  • Prepared delay analysis programme to back up Compensation Events
  • Final Accounted and closed out project

Bos Projects Consultancy provided commercial support for the Road Projects listed below:

A14 Hill House viaduct repairs; A12 Kelvedon Average Speed Cameras PPP; A12 Hughes Corne Average Speed Cameras; A11 Besthorpe to Spooner Row; A12 Kelvedon Phase 1 North bound Resurfacing; A120 Wix Bypass; A47 Easton RBT Renewal; A11 Red Lodge Carriageway Resurfacing; A14 Woolpit WB Main Carriageway Resurfacing; A47 Dereham Bypass (single C’Way Concrete Section); A47 Kings Lynn to North Runcton Resurfacing EB; A14 Pesthouse Lane BJR; A47 Thorney Knarr Fen Junction; A11 Tuttles; A47 Oversley Lodge; A47 Norwich Road; A12 Old London Road Service Road; A12N Lowestoft Police YBM; A47 Dereham Further Fatal Improvements; A14 Barrow Heath Bridge Joint replament; A12 Brook St TD19/06 Improvements; A14 Sign Renewals; A12 Marks Tey Service Rd MDS; A120 Pellens Corner Average Speed Cameras; A47 Gressenhall Tourist Signs; A47 Hockering Anti Dazzle Fence; A14 J55 Park Ride Sign; A14 Orwell Temp Signs; A12 J11-J12 Slip Road Resurfacing; A14 J47 Woolpit No Entry Improvements; A47 Kings Lynn Drainage; A120 Houchins Lane Junction Improvements; A47 J16 to J15 Cway WB Patch; A47 North Burlingham EB; A14 Crossways I/C Bridge Joint Repairs; 47 Link O Guyhirn – Redmoor; A47 Hardwick Rbt Gyratory; M11 J7 NB Exit Slip Resurfacing; M11 J7 SB Entry Slip Resurfacing; M11 J7 NB Entry Slip Resurfacing; A47 Longwater Junction Bridge Joint Repairs; M11 Stansted Park & Milkwood Bridge Joint Repairs; A12 St Peters Street to Battery Green Rbt SB; A12 Battery Green to Station Square SB; A14 River Kennet & Snailwell Rd Bridge Joint Repairs; A12 J33-J31 S&NB Resurfacing Pre-Works; A12 J11-J12 N&SB Resurfacing Pre-Works; A12 J11-J12 NB & SB Resurfacing; A12 J33-J31 SB & NB Resurfacing